Ciutadella Sud has completed the partial replacement of its sewage network, working on the fibre cement section that connects the pumping station to the treatment plant. The work upgrades outdated infrastructure and improves the reliability of the system that serves the city centre and urban developments in the south, reducing breakdowns and supporting coastal protection.
Project for the partial replacement of the wastewater treatment network in Ciutadella Sud (CIUTADELLA, MENORCA)
Minorca (Ciutadella de Menorca)
Govern de les Illes Balears
Agència Balear de l'Aigua i la Qualitat Ambiental (ABAQUA)
ITS2019-150
322.635 €
322.635 €
301.623 €
2019
Executed
Environment
Executed: 93.49%
05.05.2021
A project to boost efficiency, ensure summer capacity and improve water quality
Menorca
129.873 €
Status: Executed
The new water infrastructure improves the water supply and protects the area’s aquifers
Mallorca
515.146 €
Status: Executed
The project allows for two-way flow between Sa Marineta and s'Estremera and improves system control
Mallorca
439.230 €
Status: Executed